Work begins to protect Teesside breakwater from ‘increasingly severe’ storms
Reporting by New Civil EngineerRead the original at newcivilengineer.com
Executive Summary
Facts Only
* Fifty-five thousand tonnes of rock is being installed by PD Ports at South Gare, breakwater, in Redcar.
* The work protects the River Tees.
* Contractors McLauglin & Harvey will work with Herbosch-Kiere on positioning granite rocks.
* Rocks weigh up to 30 tonnes each and are predominantly below the waterline.
* The first phase involves installing 15,000 tonnes of high-density granite from Norway.
* A second phase is planned for summer 2027 with another 40,000 tonnes of rock installation.
* Testing included physical modelling at HR Wallingford in Oxfordshire.
* A 1:50 scale model was tested against a 1-in-200-year storm event involving a 9.2m wave.
* The research, surveys, design development, and modelling took 18 months.
* PD Ports holds legal responsibility as the Statutory Harbour Authority for the River Tees.
Full Take
From the original · New Civil Engineer
Around 55,000t of rock is being installed by PD Ports at South Gare, breakwater, in Redcar, which protects the River Tees, in response to increasingly severe storm conditions.Read the full story at newcivilengineer.com